Welcome to the Timeline Page for the Downtown Lake Oswego 137 Redevelopment

WEEKLY UPDATE

Interior Finishes Give Definition to the Future Homes in The Windward

The English Tudor inspired Windward along First Street continues to get interior definition as appliances, trim, kitchen cabinets, countertops and floors are installed. The work on Second Street alongside the Arts and Crafts Windward continues this coming week with paving scheduled to start on September 25. On the exterior of the Oregon Rustic inspired Windward along “A” Av stone veneer work will be noticeable next week.

Go to our facebook page to see photos.

www.facebook.com/TimelineLO137

Here are the construction activities happening at The Windward this coming week.

The Windward along “A” Avenue – Oregon Rustic Inspired

On the exterior, chimney stone is being finished up on the SW elevation Thursday, Sept. 14 and scaffolding will be removed following the stone install. On the SE elevation, insulation and cement board is being finished up this week and next week the stone veneer will begin install. Inside the building, the appliances were delivered on the East side of the level 2 units on Monday and paint trim and millwork are ongoing. On the West side, flooring is finishing up this week and the doors are now being installed. On the 4th floor, drywall is finished on the East units and crews are currently taping the units. Paint is scheduled to start near the end of the month. In the West units, drywall is currently being installed on the walls and ceilings with taping scheduled to begin in 2 weeks.

The Windward along Second Street – Arts and Crafts Inspired

The waterproofing of the terrace deck and conservatory balconies is finishing up this Friday, September 15. Brick has started on the North face of the South wing in the Courtyard and will continue for the next two weeks. The East elevation facing the courtyard is being painted this week. Chimney brick is being finished on the South elevation of the North wing this week. Next week insulation will be installed in this area and stucco will be installed the following week. The goal is to get the interior building elevations in the Courtyard complete in order to begin waterproofing the courtyard near the end of the month. Inside the building, framing and ceilings are installed on floors P1 through Level 1. Crews have framed the interior walls of Level 2 this week and are working on framing the ceilings. On the 3rd floor, spray foam work is ongoing and is working North to South in the building. Both of the elevator work is ongoing, these are almost complete. The work in 2nd Street is ongoing, the first paving lift is scheduled for 9/25.

The Windward along First Street – English Tudor Inspired

Brick installation is ongoing at the chimneys. On the exterior, storefront continues to be installed on the South elevation. After the South elevation is complete, the storefront installers will move to the SE elevation. Paint was finished on the NW elevation last week. Brick was completed last week on the SW elevation and the planters in this area are being formed up this week and next. Inside the building, lights and trim were installed this week on the 2nd floor. On the 3rd floor, crews are finishing taping the North units this week and will start painting today. On the 4th floor, sinks and countertops are being installed this week and flooring will begin next week on the North units. The vanities are being installed this week in the South units.

Below is what will be happening on the Block this coming week.

Click regularly to our Facebook page www.facebook.com/TimelineLO137for up to the minute news.

Time Line LO

Questions Regarding Project Site:
Dan Armstrong                (503) 937-9117           dan.armstrong@lewisbuilds.com

Questions Regarding Construction:
Matt Baker                        (503) 937-9117            matt.baker@lewisbuilds.com

Comments or Concerns:
Elaine Franklin                 (503) 819-2647         elainefranklin1@aol.com

Questions from Media:
Elaine Franklin                 (503) 819-2647         elainefranklin1@aol.com

Commercial/Retail Leasing:
Kathleen Healy                (503) 274-0211          kathleen@cra-nw.com
Scott Buth                        (503) 274-0211          scott@cra-nw.com
Ashley Heichelbech       (503) 274-0211          ashley@cra-nw.com

Residential Leasing:

livethewindward.com    (503) 636-1152

Construction Project Office –  457 Second Street, Lake Oswego

September 14, 2017

Below is what will be happening on the Block this coming week.

Click regularly to our Facebook page www.facebook.com/TimelineLO137 for up to the minute news.

September 14, 2017
Here is what will be happening this coming week.

Scaffolding will be removed at SW elevation of The Windward along “A”

Crews will continue to install insulation and cement board on the SE elevation of The Windward along “A”.

Stone veneer will begin to be installed on the SE elevation of The Windward along “A”.

Paint trim and millwork ongoing in the east units of Level 2 of The Windward along “A”.

In West units of Level 2 of The Windward along “A” crews are finishing flooring.

Doors installed in West units of Level 2 of The Windward along “A”.

Taping of West units on 4th floor of The Windward along “A”.

Waterproofing of the terrace deck and balconies is finishing at The Windward along Second Street.

Chimney brick installation is finishing on South elevation of the North wing of The Windward along Second Street.

Insulation will be installed on South elevation of the North wing of The Windward along Second Street.

Window installation for the rest of September on all levels of The Windward along Second Street.

Framers will frame in ceilings on Level 2 of The Windward along Second Street.

On 3rd floor of The Windward along Second Street spray foam is ongoing working North to South.

Elevator work is ongoing in The Windward along Second Street.

Work on Second Street is ongoing.

Brick work around the chimneys continues at The Windward along First Street.

Storefront installation continues on South elevation at The Windward along First Street.

Planters will be formed on SW elevation of The Windward along First Street.

Crews will finish taping North units on 3rd floor of The Windward along First Street.

Painting of North units of 3rd floor in The Windward along First Street starts Friday, September 15.

On 4th floor of The Windward along First Street, sinks are being installed in North units.

Countertop installation finishing on the 4th floor of the North units of The Windward along First Street.

Flooring begins in the North units of The Windward along First Street.

Vanities installed in South units of The Windward along First Street.

As always don't hesitate to call or email any of the people listed on the left side of this page.

Project News Updates

Kessi, Wizer, city sign off on closing documents for development of Block 137

Written by Saundra Sorenson .  Originally published in the Lake Oswego Review 10/22/15. It’s official. Developer Patrick Kessi, property owner Gene Wizer and representatives for the city signed closing documents this week on Block 137, clearing the way for the first mixed-use...

Groundbreaking sets the stage for Wizer Block construction

Story written by Saundra Sorenson.  Originally publish on the Lake Oswego Review website 10/19/2015. It was only four shovelfuls of dirt, tossed into a waiting skid-steer loader. But for the honorary construction workers who gathered in the southeast parking lot of the Wizer...

Certificate of Compliance for Hazardous Materials Abatement

Certificate of Compliance for Asbestos and Lead Paint Removal – Block 137

Citizen’s View: Looking toward tomorrow

Letter by John Beardsley.  Originally published in the Lake Oswego Review 10/1/15. How perceptive was the last paragraph in Victor Nelson’s letter to the editor (“Change and progress,” Sept. 24)? At the end of his letter, Nelson included a David Ben Gurion quote — “It’s not...