Welcome to the Timeline Page for the Downtown Lake Oswego 137 Redevelopment

WEEKLY UPDATE

Working to beat the Rain

There will be construction work on The Windward Block this weekend. Crews will be working trying to take advantage of the nice weather and must continue waterproofing, sealant, and paint activities. There should be minimal noise, possibly the use of one or two aerial lifts with just a little engine noise.

Saturday is the LO Farmer’s Market last day of the season so shop the region’s finest products in sunny weather!

Starting October 16th the right lane in the Eastbound direction on “A” Ave. will be closed to install new sidewalk and curb along the road.

Go to our facebook page to see photos.

www.facebook.com/TimelineLO137

Here are the construction activities happening at The Windward this coming week.

The Windward along “A” Avenue – Oregon Rustic Inspired

On the exterior, crews are installing the stone veneer. Inside the building, the units on the East side of the 3rd floor are being taped this week. Paint started in these units Friday October 13. On the West side of the 3rd floor, taping also began Friday, October 13 and painting will start near the end of next week. On the 4th floor, the East unit cabinets were installed and countertops are now being installed. In the West units, crews are working on painting this week and next week. Starting October 16th, the right lane in the East bound direction on A Ave. will be closed along the development in order to install new sidewalk and curb along the road. This lane closure will last until November 3rd.

The Windward along Second Street – Arts and Crafts Inspired

Hot rubber waterproofing is underway in the Courtyard area starting in the SW corner. The roofers are working to finish up the weather barrier on the SW corner of the building. The rain has not helped this cause. Brick was installed on the East elevation of the South wing last week. Stucco has been installed on the South elevation of the North wing in the courtyard last week and it has been painted this week. Inside the building, drywall is almost complete on the ground level and crews will start taping once the drywall is complete. Insulation was installed last week on the 1st floor North units and the South units are currently being insulated. Mechanical, electrical, and plumbing are continuing their rough-in on the 2nd and 3rd floor of the building.

The Windward along First Street – English Tudor Inspired

On the exterior, storefront continues to be installed on the South and SE elevations. The SE elevation was painted last week. Siding is finishing up on the North elevation this week. Inside the building, countertops were installed in the North units on level 3 last week and flooring is ongoing in these units. In the South units, the cabinets have been installed, countertops are finishing up Friday, October 13 and flooring will begin next week. On the 4th floor, the units on the North end are being trimmed out and this will continue next week. In the South units, flooring is completed. The doors and hardware are being installed this week and next week.

Below is what will be happening on the Block this coming week.

Click regularly to our Facebook page www.facebook.com/TimelineLO137for up to the minute news.

Time Line LO

Questions Regarding Project Site:
Dan Armstrong                (503) 937-9117           dan.armstrong@lewisbuilds.com

Questions Regarding Construction:
Matt Baker                        (503) 937-9117            matt.baker@lewisbuilds.com

Comments or Concerns:
Elaine Franklin                 (503) 819-2647         elainefranklin1@aol.com

Questions from Media:
Elaine Franklin                 (503) 819-2647         elainefranklin1@aol.com

Commercial/Retail Leasing:
Kathleen Healy                (503) 274-0211          kathleen@cra-nw.com
Scott Buth                        (503) 274-0211          scott@cra-nw.com
Ashley Heichelbech       (503) 274-0211          ashley@cra-nw.com

Residential Leasing:

livethewindward.com

Construction Project Office –  457 Second Street, Lake Oswego

October 13, 2017

October 13, 2017
Here is what will be happening this coming week.

Stone veneer continues to be installed on the exterior of The Windward along “A”.

Taping of the East units on 3rd floor of The Windward along “A” continues.

On West side of the 3rd floor of The Windward along “A” taping continues.

Paint will begin at the West units on 3rd floor of The Windward along “A”.

Countertops will be installed in the bathrooms of 4th floor of The Windward along “A”.

In the West units of The Windward along “A” the crews will continue to paint next week.

Hot rubber waterproofing continues in the SW corner of the Courtyard area of The Windward along Second Street.

The roofers are finishing the weather barrier on the SW corner roof on The Windward along Second Street.

Inside on the North side of the Ground floor of The Windward along Second Street drywall will be completed.

Inside on the South side of the Ground floor of The Windward along Second Street drywall will be completed and taping will start.

Mechanical, electrical, and plumbing are continuing their rough-in on the 2nd and 3rd floor of The Windward along Second Street

Storefront installation continues on South and S.E. elevations at The Windward along First Street.

The siding will be finished on the North elevation at The Windward along First Street.

Flooring begins in South units at The Windward along First Street.

North units on the 4th floor at The Windward along First Street will be trimmed out.

In the South units at The Windward along First Street doors and hardware will continue to be installed.

As always don't hesitate to call or email any of the people listed on the left side of this page.

Project News Updates

PIZZA, SUSHI & ICE CREAM!

Tour of downtown Lake Oswego includes a stop at The Windward, where five businesses have signed the first retail leases Review Photo: Vern Uyetake – Developer Patrick Kessi (right) leads a tour of one of the ground-floor retail spaces in The Windward, a mixed-use...
Comments : 0

Lake Oswego Wizer Block is now ‘The Windward’

Article by Pamplin Media Group. Originally publish online at The Lake Oswego Review 6/8/17.   Mixed-use development’s new name reflects it prime location next to Oswego Lake The Windward’s logo is designed to signify decades of water-related activities that helped...
Comments : 0

WHAT GOES UP…

Written by Anthony Macuk.  Originally published online Wednesday, 24 May 2017 by the Lake Oswego Review.  With the vertical stage of construction all but done, crews remove the tallest of two Wizer Block cranes in downtown Lake Oswego REVIEW PHOTO: ANTHONY MACUK – An...
Comments : 0

A TALL TALE

Article by Anthony Macuk.  Originally publish online at The Lake Oswego Review 5/11/17.   Lake Oswego’s Wizer Block construction project is about to hit another milestone: the removal of one of the two tall cranes that tower over the mixed-use development. But before that...
Comments : 0